TM 5-3895-372-34
b.
Installation.
(1) Tie a suitable rope (2) to the left end of cement feeder (1, fig. 2-30), routed up through the cement bin to
the first mechanic. Second and third mechanics lift and guide cement feeder onto two 1" X 2" boards (13); remove rope.
(2) Using a prybar, raise cement feeder (1) into position and aline mounting holes. Ensure gasket (15) is in
position and secure with ten bolts (3), lockwashers (17), and nuts (18).
(3)
Reconnect cement feeder shaft. (Refer to TM 5-3895-372-20.)
(4)
Reconnect sprocket chain (8) with master link (9). (Refer to TM 5-3895-372-20.)
(5) Position hammer assembly (12) and insert hammers through dust shield and secure hammer assembly
(12) to cement feeder (1) with four bolts (10), and washers (11).
(6)
Position valve mounting bracket (8, fig. 2-29) and secure to cement feeder with two bolts (7).
(7)
(8)
Install meter register cable (5, fig. 2-29) and tighten setscrew (1).
(9)
Install lower access panel (4, fig. 2-28) and secure with three bolts (6) and star washers (5).
(10) Lower upper access panel (1) and secure with retaining clips (2).
(12) Replace two access panels (1) on right side of vehicle and secure with retaining clips (2).
2-45