4-15. UNIT MAINTENANCE INTRODUCTION.
Instructions in this section provide general procedures to be followed for inspection, removal, cleaning, repair,
replacement, or installation of components and testing authorized at the unit level as specified by the MAC.
4-16. SERVICING EQUIPMENT.
a. Perform the PMCS contained in Tables 2-2 and 4-2.
b. Lubricate all points as shown in the Lubrication Chart, Figure 3-1.
c. Schedule the next preventive maintenance checks and services on DD Form 314, Preventive Maintenance
Schedule and Record.
4-17. JACKING LIFT POINTS.
Gross vehicle weight is 14,980 lbs (6801 kg). To support vehicle, jackstands must have a 10,000 lb
(4537 kg) capacity.
Jacking of vehicle must be done with wheels blocked, hand brakes set, and rotor assembly fully raised. Select jack
points only on front axle and rear hitching frame. Jacks shall not be used to support vehicle during maintenance
procedures. Personnel must be careful to keep body parts out from under vehicle while it is in raised position. Jacks
and jack stands must be able to support 10,000 lb (4537 kg).
4-154