Table 3-1. Operator/Crew Preventive Maintenance Checks and Services (Continued)
B - Before
D - During
A - After
W - Weekly
M - Monthly
OPERATOR PMCS - M919 CONCRETE MOBILE MIXER BODY
Item
Interval
ITEM TO BE INSPECTED
FOR READINESS REPORTING
Procedure: Check For And Have Repaired
Equipment is not Ready/
No.
B
DAWM
Filled Or Adjusted As Needed
Available If:
LIQUID ADMIX
(when used)
46
Check low flow and hi-flow
Class III leaks are evident.
tanks for leaks.
47
Unless told otherwise, drain and flush liquid
admix tanks at the end of the day.
48
Check air pressure gage for
Gage inoperative or 15
15 PSI set with air regulator.
PSI cannot be obtained.
49
Check sight gage on tank.
TA 075538